Committees & Groups

Issue Details

New Service Requests Deficiency Review Requirements

As a result of the systemic increase in queue volume, particularly at the end of a Queue window, consider enhancements to the date by which Generation Interconnection Requests must be submitted, and to the five Business Day period for PJM to undertake a deficiency review of a New Service Request, or review the information provided by an Interconnection Customer in response to the initial deficiency notice.

Proposed Timeline

Issue initiated: 5.11.2021
Work begins: 3.9.2021
Target Completion: 6.23.2021
Actual Completion: 8.23.2021

Issue Details

Stakeholder Body Planning Committee
Facilitator Souder, David W.
Subject Matter Expert Connell, Jason P.
PC Approval Date 5.11.2021
MRC Approval Date 5.26.2021
MC Approval Date 6.23.2021
Problem Statement/
Issue Charge First Read
3.9.2021
Issue Catalyst PJM
Issue Status Closed
Manual Changes Yes
Agreement Changes Open Access Transmission Tariff
  • Stakeholder Process Step

  • Completed Approved
  • Completed Education
  • Completed Interest
  • Completed Design
  • Completed Options
  • Completed Packages
  • Completed Consensus
  • Completed Review
  • Completed Completed
6.24.2021 -Filing-
Docket No. ER21-2203-000  PDF
8.23.2021 -Order-
Docket No. ER21-2203-000  PDF