Generating Facility |
$4,000 per MW is required.
The MW values used in the calculation is the greater of (1) and (2) specified in the application:
(1) MW energy (e.g., Maximum Facility Output)
(2) MW capacity (e.g., Capacity Interconnection Rights) |
Study deposit required is as follows:
0 - 20MW — $75,000
> 20 - 50MW — $200,000
> 50 - 100MW — $250,000
> 100 - 250MW — $300,000
> 250 - 750MW — $350,000
> 750MW — $400,000
|
Merchant Transmission Facility Specifications |
$4,000 per MW is required.
The MW values used in the calculation is the greater of (1) and (2) specified in the application:
(1) MW energy (e.g., Maximum Facility Output)
(2) MW capacity (e.g., Capacity Interconnection Rights) |
Study deposit required is as follows:
0 - 20MW — $75,000
> 20 - 50MW — $200,000
> 50 - 100MW — $250,000
> 100 - 250MW — $300,000
> 250 - 750MW — $350,000
> 750MW — $400,000
|