Committees & Groups

Planning Committee

The Planning Committee (PC) is established under the Operating Agreement WEB | PDF and has the responsibility to review and recommend system planning strategies and policies as well as planning and engineering designs for the PJM bulk power supply system to assure the continued ability of the member companies to operate reliably and economically in a competitive market environment. Additionally, the PC makes recommendations regarding generating capacity reserve requirement and demand-side valuation factors.

Special Session Issues

Capacity Interconnection Rights for ELCC Resources
Critical Infrastructure Stakeholder Oversight
Storage as a Transmission Asset
Merchant Transmission & Offshore Wind (Suspended)

View all issues the PC is currently tracking.

Chair: Rebecca Carroll
Secretary:
 Ashwini Bhat

During the meeting, if you are experiencing issues with connectivity or teleconference, please contact Meeting Support. For registration issues, contact PJM.

Roster PDF | Updates

 



Training Video

Community User Guide PDF

Date
Charter PDF
8.12.2016
Single Meeting Voting Proxy  
Long-Term Transmission Planning: Questions on the NOPR for Stakeholder Feedback DOC  

Meeting Materials

 2.21.2024 - PC - ELCC Education Session

 2.16.2024 - PC - ELCC Education Session

 10.3.2023 - Planning Committee

10.2.2023 Agenda  PDF
10.2.2023 Agenda-doc  DOC
9.7.2023 Draft Minutes -PC- 9.5.2023  PDF
9.26.2023 Item 04A - M19 Attachment B-Problem Statement  PDF
9.26.2023 Item 04B - M19 Attachment B-Issue Charge  PDF
9.29.2023 Item 04C - M19-Attachment B-Redline  PDF
9.29.2023 Item 04D - M19-Attachment B-Clean  PDF
9.26.2023 Item 04E - M19 Attachment B-Executive Summary  PDF
9.29.2023 Item 04 - Manual 19-Attachment B Load Forecast Adjustment - Manual Changes  PDF
10.2.2023 Item 05A - PJM 2023 RRS Report  PDF
10.20.2023 Item 05B - RTO Residuals and RTO CP1 Comparison  XLS
9.26.2023 Item 05 - PJM 2023 RRS Results  PDF
9.26.2023 Item 06A - M19-Periodic Review-Redline  PDF
9.26.2023 Item 06B - M19-Periodic Review-Clean  PDF
9.26.2023 Item 06C - M19 Periodic Review Executive Summary  PDF
9.26.2023 Item 06 - Manual 19-Periodic Review - Manual Changes  PDF
9.26.2023 Item 07A - Manual-14B - Version 55-Redline  PDF
9.26.2023 Item 07B - Manual-14B - Version 55-Clean  PDF
9.26.2023 Item 07C - Manual 14B-Executive Summary-Manual Changes  PDF
9.26.2023 Item 07 - Manual-14B Update - Periodic Review  PDF
10.3.2023 Item 08 - Reliability Compliance Update  PDF
9.27.2023 Item D1 - Manual 03 - V65-Preview  PDF
9.27.2023 Item D2 - Manual 03 - V65-Redline  PDF
9.27.2023 Item D3 - Manual 03 - V65-Executive Summary Manual Changes  PDF
9.27.2023 Item D - Manual 03 - Revision 65  PDF
11.1.2023 Minutes  PDF
10.5.2023 Posting-Score-Card  XLS

 7.11.2023 - Planning Committee

7.3.2023 Agenda  PDF
7.3.2023 Agenda-doc  DOC
6.27.2023 Draft Minutes - PC - 06.06.2023  PDF
7.6.2023 Item 04A - 2023 PC Work Plan  XLS
7.6.2023 Item 04 - Planning Committee - 2023 Work Plan  PDF
7.5.2023 Item 05A - IPRTF Manuals - Executive Summary  PDF
7.5.2023 Item 05B - M14A-V30 - Redline  PDF
7.5.2023 Item 05C - M14A-V30 - Preview  PDF
7.5.2023 Item 05D - M14B-V53 - Redline  PDF
7.5.2023 Item 05E - M14B-V53 - Preview  PDF
7.5.2023 Item 05F - M14C - Redline  PDF
7.5.2023 Item 05G - M14C - Preview  PDF
7.5.2023 Item 05H - M14E-V09 - Redline  PDF
7.5.2023 Item 05I - M14E-V09 - Preview  PDF
7.5.2023 Item 05J - M14G-V8 - Redline  PDF
7.5.2023 Item 05K - M14G-V8 - Preview  PDF
7.5.2023 Item 05L - M14H - Preview  PDF
7.3.2023 Item 05 - Manual Changes  PDF
7.5.2023 Item 05M - M20-V13 - Redline  PDF
7.5.2023 Item 05N - M20-V13 - Preview  PDF
7.5.2023 Item 05O - M21A-V2 - Redline  PDF
7.5.2023 Item 05P - M21A-V2 - Preview  PDF
7.5.2023 Item 05Q - M21 - Redline  PDF
7.5.2023 Item 05R - M21 - Preview  PDF
7.5.2023 Item 06A - M14B Version 54 Clean  PDF
7.5.2023 Item 06B - M14B Version 54 Redline  PDF
7.6.2023 Item 06C - Issue Charge TPL-001-5.1  PDF
7.6.2023 Item 06D - Problem Statement TPL-001-5.1  PDF
7.5.2023 Item 06 -TPL-001-5 M14B Changes  PDF
7.13.2023 Item 07 - PJM Load Model Selection-2023 Reserve Requirement  PDF
7.3.2023 Item 08 - Reliability Compliance Update  PDF
8.8.2023 Minutes  PDF
7.13.2023 20230711-posting-score-card  XLS

 6.6.2023 - Planning Committee

5.31.2023 Agenda  PDF
5.31.2023 Agenda-doc  DOC
5.14.2023 Draft Minutes - PC - 05.09.2023  PDF
5.30.2023 Item 04A - CIR Transfer Problem Statement  PDF
5.30.2023 Item 04B - CIR Transfer Issue Charge  PDF
6.6.2023 Item 04C - CIR Transfer Approved Issue Charge - post-meeting  PDF
5.30.2023 Item 04 - Enhancing CIR Transfer Efficiency  PDF
5.30.2023 Item 05 - 2023 RRS Assumptions  PDF
5.30.2023 Item 05A - 2023 RRS Assumptions Document  PDF
5.30.2023 Item 05B - 2023 RRS Assumptions Table  PDF
5.30.2023 Item 06A - Manual Updates - Executive Summary  PDF
5.30.2023 Item 06B - M14A - Clean  PDF
5.30.2023 Item 06C - M14A - Redline  PDF
5.30.2023 Item 06D - M14B - Clean  PDF
5.30.2023 Item 06E - M14B - Redline  PDF
5.30.2023 Item 06F - M14C - Clean  PDF
5.30.2023 Item 06G - M14C - Redline  PDF
5.30.2023 Item 06H - M14E - Clean  PDF
5.30.2023 Item 06I - M14E - Redline  PDF
5.30.2023 Item 06J - M14G - Clean  PDF
5.30.2023 Item 06K - M14G - Redline  PDF
5.30.2023 Item 06L - M20 - Clean  PDF
5.30.2023 Item 06 - Manual Updates - Presentation  PDF
5.30.2023 Item 06M - M20 - Redline  PDF
5.30.2023 Item 06N - M21 - Clean  PDF
5.30.2023 Item 06O - M21 - Redline  PDF
5.30.2023 Item 06P - M21A - Clean  PDF
5.30.2023 Item 06Q - M21A - Redline  PDF
5.30.2023 Item 06R - M14H - Clean  PDF
5.30.2023 Item 07 - PPL FERC 715 Update  PDF
5.30.2023 Item 08 - Transmission & Substation Subcommittee Update  PDF
6.6.2023 Item 09 - Reliability Compliance Update  PDF
7.13.2023 Minutes  PDF
6.7.2023 20230606-posting-score-card  XLS

 4.12.2022 - Planning Committee

4.11.2022 Agenda  PDF
4.11.2022 Agenda  DOC
5.13.2022 Minutes  PDF
4.6.2022 Draft Minutes - PC - 3.8.2022  PDF
4.5.2022 Item 5 - 2022 Work Plan  PDF
4.5.2022 Item 6A - Manual 14F - Updates  PDF
4.5.2022 Item 6B - Manual 14F - Executive Summary  PDF
4.5.2022 Item 6C - Manual 14F - Redline  PDF
4.5.2022 Item 6D - Manual 14F - Preview  PDF
4.5.2022 Item 7A - Manual 21A - Presentation  PDF
4.5.2022 Item 7B - Manual 21A - Problem Statement  PDF
4.5.2022 Item 7C - Manual 21A - Issue Charge  PDF
4.5.2022 Item 7D - Manual 21A - Revisions - Executive Summary  PDF
4.5.2022 Item 7E - Manual 21A - Revision - Redline  PDF
4.5.2022 Item 7F - Manual 21A - Revision - Clean  PDF
4.5.2022 Item 8 - Interconnection Planning Subcommittee Charter  PDF
4.5.2022 Item 9A - Designated Entity Agreement (DEA) Update  PDF
4.5.2022 Item 9B - DEA - Problem Statement  PDF
4.5.2022 Item 9C - DEA Issue Charge  PDF
4.6.2022 Item 9D - Information Only - OA Definitions C- D  PDF
4.6.2022 Item 9E - Information Only - OA Schedule 6, Section 1.5   PDF
4.7.2022 Item 10A - Draft RSCS Charter - Current  PDF
4.7.2022 Item 10B - Draft RSCS Charter - Redline  PDF
4.5.2022 Item 11 - Capacity Interconnection Rights for ELCC Resources Update  PDF
4.5.2022 Item 12 - Generator Deliverability Proposal Update  PDF
4.5.2022 Item 13 - Interconnection Queue Status Update  PDF
4.5.2022 Item 14A - Informational Only - Manual 03 - Updates  PDF
4.5.2022 Item 14B - Informational Only - Manual 13 - Executive Summary  PDF
4.5.2022 Item 14C - Informational Only - Manual 03 - Revision 61 - Redline  PDF
4.5.2022 Item 14D - Informational Only - Manual 03 - Revision 61 - Preview  PDF
4.5.2022 Item 15 - Reliability Compliance Update  PDF
4.7.2022 Item 16A - Interconnection Customer Coalition Amendment to PJM Transition Proposal  PDF
4.7.2022 Item 16B - Dominion/PSEG/Orsted Friendly Amendment - follow up from 3.23.2022 MRC  PDF
4.11.2022 Item 16C - Information Only - PJM Tariff, Part VIII Site Control - Dominion/PSEG/Orsted Suggested Revision  PDF
4.11.2022 Item 16D - PJM Generation Interconnection Queue Reform PURPA Presentation  PDF
4.14.2022 Posting Score Card  XLS

 3.8.2022 - Planning Committee

3.8.2022 Agenda  PDF
3.8.2022 Agenda  DOC
2.23.2022 Item 3 - Draft Minutes - PC - 2.8.2022  PDF
4.14.2022 Minutes  PDF
3.1.2022 Item 4A - Deactivation Problem Statement - Education  PDF
3.1.2022 Item 4B - Problem Statement Deactivation - Process Timeline  PDF
3.1.2022 Item 4C - Issue Charge Deactivation Process - Process Timeline  PDF
3.1.2022 Item 4D - Information Only - Manual 14D - Revision 59 - Redline  PDF
3.1.2022 Item 4E - Information Only - Manual 14D - Revision 59 - Preview  PDF
3.1.2022 Item 4F - Information Only - OATT Section 113  PDF
3.1.2022 Item 4G - Information Only - OATT Attachment M Appendix  PDF
3.1.2022 Item 5A - Manual 14F Update  PDF
3.1.2022 Item 5B - Manual 14F - Executive Summary  PDF
3.4.2022 Item 5C - Manual 14F - Biennial Review - Redline  PDF
3.4.2022 Item 5D - Manual 14F - Biennial Review - Clean  PDF
3.1.2022 Item 6A - Manual 21A - Extension of Voluntary Unit Specific Data Submission - Presentation  PDF
3.1.2022 Item 6B - Manual 21A - Extension of Voluntary Unit Specific Data Submission - Problem Statement  PDF
3.1.2022 Item 6C - Manual 21A - Extension of Voluntary Unit Specific Data Submission - Issue Charge  PDF
3.1.2022 Item 6D - Manual 21A Revisions - Executive Summary  PDF
3.1.2022 Item 6E - Manual 21A Revisions - Redline  PDF
3.1.2022 Item 6F - Manual 21A Revisions - Clean  PDF
3.1.2022 Item 7 - Capacity Interconnection Rights for ELCC Resources Update  PDF
3.1.2022 Item 8 - Generator Deliverability Proposal - Revised Timeline  PDF
3.1.2022 Item 10A - Documenting the Appropriate UFLS Requirements Applicable to EKPC  PDF
3.1.2022 Item 10B - Information Only - EKPC Problem Statement  PDF
3.1.2022 Item 10C - Information Only - EKPC Issue Charge UFLS  PDF
3.1.2022 Item 11 - PJM Study - Illinois Clean Energy Jobs Act  PDF
3.1.2022 Item 12A - TTMS Charter  PDF
3.1.2022 Item 12B - TTMS Charter - Redline - V2  PDF
3.1.2022 Item 13 - PJM Reliability Compliance Update  PDF
3.11.2022 Posting Score Card  XLS

 2.8.2022 - Long Term Transmission Planning Reform Workshop - Session 1

 2.8.2022 - Planning Committee

2.4.2022 Agenda  PDF
2.4.2022 Agenda  DOC
3.11.2022 Minutes  PDF
1.18.2022 Item 3 - Draft Minutes - OC - 1.11.2022  PDF
2.1.2022 Item 4 - PJM Retiring Use of Weak Encryption of Voting  PDF
2.1.2022 Item 5 - Browserless API Two-Factor Authentication PKI Update  PDF
2.7.2022 Item 6A - IPRTF Transition Proposal Packages Presentation  PDF
2.1.2022 Item 6 - IPRTF Matrix - Version 6  XLS
2.1.2022 Item 6B - Amendment to PJM Transition Proposal IC Coalition  PDF
2.1.2022 Item 7A - TO/TOP Matrix Review - Version 16 - Second Read  PDF
2.1.2022 Item 7B - TO/TOP Matrix - Version 16 - Redline  XLS
2.2.2022 Item 8A - Deactivation Problem Statement Education  PDF
2.1.2022 Item 8B - Deactivation Process Timeline - Problem Statement  PDF
2.1.2022 Item 8C - Deactivation Process Timeline - Issue Charge  PDF
2.1.2022 Item 8D - Information Only - Manual 14D - Revision 59 - Redline  PDF
2.1.2022 Item 8E - Information Only - Manual 14D - Revision 59 - Preview  PDF
2.3.2022 Item 8F - Information Only - OATT Section 113  PDF
2.3.2022 Item 8G - Information Only - OATT Attachment M Appendix  PDF
2.1.2022 Item 9 - PC Special Session - Capacity Interconnection Rights for ELCC Resources  PDF
2.1.2022 Item 10 - Revised Generator Deliverability Proposal Development Timeline  PDF
2.2.2022 Item 11 - Queue Status Update  PDF
2.3.2022 Item 12 - New Jersey Offshore Wind SAA Agreement Filing  PDF
2.1.2022 Item 14 - Reliability Compliance Update  PDF
1.12.2022 TOA-AC Notice of Transmission Owners Consultation with the MC  PDF
2.10.2022 Posting Score Card  XLS

 1.11.2022 - Planning Committee

1.10.2022 Agenda  PDF
1.10.2022 Agenda  DOC
2.10.2022 Minutes  PDF
12.21.2021 Item 3 - Draft Minutes - PC - 12.14.2021  PDF
1.4.2022 Item 4 - 2022 Work Plan  PDF
1.11.2022 Item 5A - IPRTF Presentation  PDF
1.4.2022 Item 5B - IPRTF Matrix - Version 5  XLS
1.6.2022 Item 5B - IPRTF Matrix - Version 6  XLS
1.6.2022 Item 6 - IPRTF/PC First Read Transition - Presentation  PDF
1.5.2022 Item 7A - Deactivation Problem Statement Education  PDF
1.5.2022 Item 7B - Problem Statement Deactivation Process Timeline  PDF
1.4.2022 Item 7C - Deactivation Process Timeline - Issue Charge  PDF
1.5.2022 Item 7D - Information Only - Manual 14D - Version 59 - Redline  PDF
1.5.2022 Item 7E - Information Only - Manual 14D - Version 59 - Preview  PDF
1.4.2022 Item 7F - Information Only - Informational Only - OATT Section 113  PDF
1.4.2022 Item 7G - Information Only - OATT Attachment M - Appendix  PDF
1.4.2022 Item 8A - TO/TOP Matrix Review - Version 16  PDF
1.4.2022 Item 8B - Draft TO/TOP Matrix - Version 16 - Redline  XLS
1.4.2022 Item 9 - Capacity Interconnection Rights for ELCC Resources  PDF
1.5.2022 Item 11 - Attachment M-3 Update  PDF
1.11.2022 Item 11B - M-3 Action Items  XLS
1.4.2022 Item 12 - Reliability Compliance Update  PDF
1.10.2022 Item X - PJM Retiring Use of Weak Encryption for Voting  PDF
1.4.2022 Informational Only - 2021/2022 Long-Term Window 1 - Carbon Impact of Selected Market Efficiency Projects  PDF
1.12.2022 Posting Score Card  XLS

 11.2.2021 - Planning Committee

11.1.2021 Agenda  PDF
11.1.2021 Agenda  DOC
12.17.2021 Minutes  PDF
10.28.2021 Item 3 - Draft Minutes - PC - 10.5.2021  PDF
10.26.2021 Item 4 - Charter  PDF
10.26.2021 Item 5 - 2021-2022 Winter Weekly Reserve Target  PDF
10.26.2021 Item 6A - Manual 14B Update  PDF
10.26.2021 Item 6B - Manual 14B - Executive Summary  PDF
10.26.2021 Item 6C - Manual 14B - Biennial Review - Redline  PDF
10.26.2021 Item 6D - Manual 14B - Biennial Review - Clean  PDF
10.26.2021 Item 6E - PJM M3 EOL  PDF
10.26.2021 Item 7A - Manual 19 - Changes  PDF
10.26.2021 Item 7B - Manual 19 - Executive Summary  PDF
10.26.2021 Item 7C - Manual 19 - Redline  PDF
10.26.2021 Item 7D - Manual 19 - Clean  PDF
11.2.2021 Item 8A - Manual 14F - Revision 8 - Changes  PDF
11.2.2021 Item 8B - Manual 14F - Revision 8 - Executive Summary  PDF
11.2.2021 Item 8C - Manual 14F - Revision 8 - Redline  PDF
11.2.2021 Item 8D - Manual 14F - Revision 8 - Clean  PDF
10.26.2021 Item 9A - Generator Deliverability Test Modifications - Manuals 14A & 14B  PDF
10.26.2021 Item 9B - Generator Deliverability - Problem Statement  PDF
10.26.2021 Item 9C - Generator Deliverability - Issue Charge  PDF
10.26.2021 Item 9D - Executive Summary  PDF
10.26.2021 Item 9E - Manual 14A Update - Redline  PDF
10.26.2021 Item 9F - Manual 14A Update - Clean  PDF
10.26.2021 Item 9G - Manual 14B - Generator Deliverability Updates - Redline  PDF
10.26.2021 Item 9H - Manual 14B - Generator Deliverability Updates - Clean  PDF
10.26.2021 Item 9I - 2020 Light Load Average Temperatures  XLS
10.26.2021 Item 10 - Queue Status Update  PDF
10.26.2021 Item 11 - PC-CIR Update  PDF
10.26.2021 Item 13 - PJM Reliability Compliance Update  PDF
11.3.2021 Posting Score Card  XLS

 10.5.2021 - Planning Committee

10.4.2021 Agenda  PDF
10.4.2021 Agenda  DOC
11.3.2021 Minutes  PDF
9.28.2021 Item 3 - Draft Minutes - PC - 8.31.2021  PDF
9.28.2021 Item 4 - Work Plan  PDF
9.28.2021 Item 5 - 2021 RRS Preliminary Assessment Results  PDF
10.1.2021 Item 5B - 2021 PJM Reserve Requirement Study  PDF
10.4.2021 Item X - 2021/2022 Winter Weekly Reserve Target  PDF
10.1.2021 Item 6A - Manual 14B - Update  PDF
10.1.2021 Item 6B - Manual 14B - Executive Summary  PDF
10.5.2021 Item 6C - Manual 14B - Biennial Review - Redline - Post Meeting  PDF
10.5.2021 Item 6D - Manual 14B - Biennial Review - Clean - Post Meeting  PDF
9.28.2021 Item 7A - Manual 19 - Changes  PDF
9.28.2021 Item 7B - Manual 19 - Executive Summary  PDF
9.28.2021 Item 7C - Manual 19 - Redline  PDF
9.28.2021 Item 7D - Manual 19 - Clean  PDF
10.4.2021 Item 8A - Manual 14F - Changes  PDF
10.4.2021 Item 8B - Manual 14F - Executive Summary  PDF
10.4.2021 Item 8C - Manual 14F - Redline  PDF
10.4.2021 Item 8D - Manual 14F - Clean  PDF
9.30.2021 Item 9A - Generator Deliverability Test Modifications - Manual 14A & 14B Update  PDF
9.30.2021 Item 9B - Manual 14A & 14B - Executive Summary  PDF
9.28.2021 Item 9C - Manual 14A Update - Redline (Corrected)  PDF
9.28.2021 Item 9D - Manual 14A Update - Clean  PDF
9.28.2021 Item 9E - Manual 14B - Generator Deliverability Updates - Redline  PDF
9.28.2021 Item 9F - Manual 14B - Generator Deliverability Updates - Clean  PDF
9.28.2021 Item 9G - 2020 Light Load Average Temperature  XLS
9.28.2021 Item 10 - Market Efficiency Process Enhancement Carbon Impact Reporting  PDF
10.5.2021 Item 11 - October PC - Capacity Interconnection Rights for ELCC Resources - Post Meeting  PDF
9.28.2021 Item 13 - Reliability Compliance Update  PDF
9.30.2021 Informational Only - Manual 03 - Revision 60 - Executive Summary  PDF
9.30.2021 Informational Only - Manual 03 - Revision 60 - Presentation  PDF
9.30.2021 Informational Only - Manual 03 - Revision 60 - Redline  PDF
10.6.2021 Posting Score Card  XLS

 9.30.2021 - Interconnection Policy Workshops - Session 6

 9.14.2021 - PC Special Session - State Agreement Approach

 6.24.2021 - Interconnection Policy Workshop - Session 2

 5.18.2021 - Interconnection Policy Workshop - Session 1

 5.11.2021 - Planning Committee

5.4.2021 Agenda  PDF
5.4.2021 Agenda  DOC
6.9.2021 Minutes  PDF
4.12.2021 Item 3 - Draft Minutes - PC - 20210406  PDF
5.4.2021 Item 4A - Interconnection Construction Service Agreement (ICSA) - Superseding Language & Automatic Termination Provision  PDF
5.4.2021 Item 4B - ICSA Superseding Language & Automatic Termination - Problem Statement  PDF
5.4.2021 Item 4C - ICSA Superseding Language & Automatic Termination - Issue Charge  PDF
5.4.2021 Item 4D - Informational Only - OATT Attachment P A2 14.1  PDF
5.4.2021 Item 4E - Information Only - OATT Attachment P - ICSA  PDF
5.4.2021 Item 5A - New Service Req Deficiency - Review Requirement  PDF
5.4.2021 Item 5B - New Service Req Deficiency - Problem Statement  PDF
5.4.2021 Item 5C - New Service Req Deficiency - Issue Charge  PDF
5.4.2021 Item 5D - Informational Only - OATT 36.1  PDF
5.4.2021 Item 5E - Informational Only - OATT 110.1  PDF
5.4.2021 Item 5F - Informational Only - OATT 111.1  PDF
5.4.2021 Item 5G - Informational Only - OATT 112.1  PDF
5.4.2021 Item 5H - Informational Only - OATT 112.1A  PDF
5.4.2021 Item 5I - Informational Only - OATT 112B.1  PDF
5.4.2021 Item 5J - Informational Only - OATT 204.2  PDF
5.4.2021 Item 5J - Informational Only - OATT L M N Definitions  PDF
5.4.2021 Item 6A - Conforming Language - Presentation  PDF
5.4.2021 Item 6B - Manual 14B Conforming Language - Executive Summary  PDF
5.4.2021 Item 6C - Manual 14F Conforming Language - Executive Summary  PDF
5.4.2021 Item 6D - Manual 14B Conforming Language - Clean  PDF
5.4.2021 Item 6E - Manual 14B Conforming Language - Redline  PDF
5.4.2021 Item 6F - Manual 14F Conforming Language - Clean  PDF
5.4.2021 Item 6G - Manual 14F Conforming Language - Redline  PDF
5.4.2021 Item 7A - Manual 21 - Update 15  PDF
5.4.2021 Item 7B - Manual 21 Revision 15 - Executive Summary  PDF
5.4.2021 Item 7C - Manual 21 Revision 15 - Redline  PDF
5.4.2021 Item 7D - Manual 21 Revision 15 - Preview  PDF
5.4.2021 Item 8A - 2021 RSS Assumptions  PDF
5.4.2021 Item 8B - RSS Assumptions Letter 2021 - Redline  PDF
5.4.2021 Item 8C - RSS Assumptions Letter 2021 - Clean  PDF
5.4.2021 Item 9A - Critical Infrastructure Stakeholder Oversight Update  PDF
5.4.2021 Item 9B - Informational Only - CISO March MRC First Read Tariff OA Revisions  PDF
5.4.2021 Item 9C - Informational Only - CISO March MRC Second Read Tariff OA Revisions  PDF
5.4.2021 Item 10 - May PC CIR Update  PDF
5.4.2021 Item 11 - Interconnection Process Reform Task Force Update  PDF
5.10.2021 Item 12 - FERC Order Rejecting ELCC  PDF
5.4.2021 Item 13 - PHI Transmission Facility Rating Change  PDF
5.4.2021 Item 14 - TSS Update  PDF
5.4.2021 Item 15 - PJM Reliability Compliance Update  PDF
4.16.2021 Information Only - Notice of PJM Transmission Owners Consultation with the Members Committee - Regarding Proposed Revisions to the PJM Tariff  PDF
5.13.2021 PC Posting Score Card  XLS

 4.6.2021 - Planning Committee

4.5.2021 Agenda  PDF
4.5.2021 Agenda  DOC
5.13.2021 Minutes  PDF
3.15.2021 Item 3 - Draft Minutes - PC - 3.9.2021  PDF
3.30.2021 Item 5 - PC Work Plan  PDF
3.30.2021 Item 6A - Capacity Interconnection Rights (CIR) for Effective Load Carrying Capability (ELCC) Resources  PDF
3.30.2021 Item 6B - CIR - Problem Statement  PDF
3.30.2021 Item 6C - CIR - Issue Charge - Redline  PDF
3.30.2021 Item 6D - CIR - Issue Charge - Clean  PDF
3.31.2021 Item 7A - Interconnection Process Reform - Presentation  PDF
3.31.2021 Item 7B - Interconnection Process Reform - Problem Statement  PDF
4.5.2021 Item 7C - Interconnection Process Reform - Issue Charge  PDF
4.1.2021 Item 8A - ICSA Superseding Language & Auto Termination  PDF
4.1.2021 Item 8B - Problem Statement  PDF
4.1.2021 Item 8C - Issue Charge  PDF
4.1.2021 Item 8D - Informational Only - OATT Attachment P A2.14.1  PDF
4.1.2021 Item 8E - Informational Only - OATT Attachment P - Interconnection Construction Service Agreement  PDF
4.1.2021 Item 8F - PS Proposed Friendly Amendment - Informational Only - OATT Attachment P A2.14.1  PDF
3.31.2021 Item 9A - MEPETF - Conforming Language - Presentation  PDF
3.31.2021 Item 9B - MEPETF - Manual 14B Conforming Language - Executive Summary  PDF
3.31.2021 Item 9C - MEPETF - Manual 14F Conforming Language - Executive Summary  PDF
3.31.2021 Item 9D - MEPETF - Manual 14B Conforming Language - Clean  PDF
3.31.2021 Item 9E - MEPETF - Manual 14B Conforming Language - Redline  PDF
3.31.2021 Item 9F - MEPETF - Manual 14B Conforming Language - Clean  PDF
3.31.2021 Item 9G - MEPETF - Manual 14F - Conforming Language - Redline  PDF
4.1.2021 Item 10A - New Service Requests - Deficiency Review Requirements  PDF
4.1.2021 Item 10B - New Service Requirement Deficiency - Problem Statement  PDF
4.1.2021 Item 10C - New Service Requirement Deficiency - Issue Charge  PDF
4.6.2021 Item 10D - Informational Only - OATT 36.1  PDF
4.5.2021 Item 10E - Informational Only - OATT 110.1  PDF
4.5.2021 Item 10F - Informational Only - OATT 111.1  PDF
4.5.2021 Item 10G - Informational Only - OATT 112.1  PDF
4.5.2021 Item 10H - Informational Only - OATT 112.1A  PDF
4.5.2021 Item 10I - Informational Only - OATT 112B.1  PDF
4.5.2021 Item 10J - Informational Only - OATT 204.2  PDF
3.31.2021 Item 11A - Manual 21 - Update 15  PDF
3.31.2021 Item 11B - Manual 21 - Revision 15 - Executive Summary  PDF
3.31.2021 Item 11C - Manual 21 - Revision 15 - Redline  PDF
3.31.2021 Item 11D - Manual 21 - Revision 15 - Preview  PDF
3.30.2021 Item 12 - Effective Load Carrying Capability Conforming Manual Language Changes  PDF
3.30.2021 Item 13 - Reliability Compliance Update  PDF
4.1.2021 Item 14A - Posting Timeline Trial  PDF
4.1.2021 Item 14B - Posting Timeline Trial - Supporting Documentation  PDF
3.30.2021 Item 15 - Emerging Technologies Forum Survey  PDF
3.31.2021 Informational Posting - Manual 03 Presentation - Revision 59  PDF
3.31.2021 Informational Posting - Executive Summary Manual 03 - Revision 59  PDF
3.31.2021 Informational Posting - Manual 03 - Revision 59 - Redline  PDF
4.5.2021 Informational Posting - Manual 03 Attachment E Automatic Sectionalizing Schemes Pending Approval & Recent Changes  PDF
4.7.2021 Posting Score Card  XLS

 3.9.2021 - Planning Committee

3.5.2021 Agenda  PDF
3.5.2021 Agenda  DOC
4.7.2021 Minutes  PDF
2.12.2021 Item 3 - Draft Minutes - PC - 2.9.2021  PDF
3.2.2021 Item 4A - Capacity Interconnection Rights for ELCC Resources  PDF
3.2.2021 Item 4B - CIR - Problem Statement - Redline  PDF
3.2.2021 Item 4C - CIR - Issue Charge - Redline  PDF
3.2.2021 Item 4D - CIR - Problem Statement - Clean  PDF
3.2.2021 Item 4E - CIR - Issue Charge - Clean  PDF
3.8.2021 Item 5 - Interconnection Process Reform Presentation  PDF
3.5.2021 Item 5A - Interconnection Process Reform - Problem Statement  PDF
3.5.2021 Item 5B - Interconnection Process Reform - Issue Charge  PDF
3.2.2021 Item 6A - New Service Requests - Deficiency Review Requirements  PDF
3.2.2021 Item 6B - New Service Requests - Review Period - Problem Statement  PDF
3.2.2021 Item 6C - New Service Requests Review Period - Issue Charge  PDF
3.2.2021 Item 6D - Informational Only - Draft OATT 36.1  PDF
3.2.2021 Item 6E - Informational Only - Draft OATT 110.1  PDF
3.2.2021 Item 6F - Informational Only - Draft OATT 111.1  PDF
3.2.2021 Item 6G - Informational Only - Draft OATT 112.1  PDF
3.2.2021 Item 6H - Informational Only - Draft OATT 112.1A  PDF
3.2.2021 Item 6I - Informational Only - Draft OATT 112B.1  PDF
3.2.2021 Item 6J - Informational Only - Draft OATT 204.2  PDF
3.2.2021 Item 7A - Interconnection Construction Service Agreement - Superseding Language & Auto Termination  PDF
3.2.2021 Item 7B - ICSA - Superseding Language & Automatic Termination Provision - Problem Statement  PDF
3.2.2021 Item 7C - ICSA - Superseding Language & Automatic Termination Provision - Issue Charge  PDF
3.2.2021 Item 7D - Informational Only - OATT Attachment P.A2.14.1  PDF
3.2.2021 Item 7E - Informational Only - OATT Attachment P - ISCA  PDF
3.3.2021 Item 8 - Attachment M-3 Update  PDF
3.2.2021 Item 9 - PJM Reliability Compliance Update  PDF
3.10.2021 Posting Score Card  XLS

 12.11.2020 - Interconnection Process Workshop 2 - Stakeholder Presentations

12.8.2020 Agenda  PDF
12.8.2020 Agenda  DOC
12.8.2020 Draft Minutes - PC Process Workshop - 10.30.2020  PDF
12.8.2020 Item 3A - Deral Danis - Queue Workshop ConnectGen  PDF
12.8.2020 Item 3B - Aaron Vander Vorst - Enel PJM Interconnection Reforms  PDF
12.8.2020 Item 3C - Deepesh Rena - Apex Clean Energy  PDF
12.8.2020 Item 3D - Takis Laios - PJM Interconnection Queue Initiative - AEP Challenges & Improvements  PDF
12.9.2020 Item 3E - Geoffrey Underwood - Prospect14  PDF
12.8.2020 Item 3F - Amber Thomas - Exelon Interconnection Challenges  PDF
12.8.2020 Item 3G - Wonbae Choi - PJM Interconnection Workshop  PDF
12.8.2020 Item 3H - John Soininen - Vepser  PDF
12.8.2020 Item 3I - Ken Foladare - Geenex  PDF
12.8.2020 Item 3J - Tom Schmidt - Establishing Retail Electric Service within the Interconnection Process  PDF
12.8.2020 Item 3K - Mike Borgatti - AWEA Comments  PDF
12.8.2020 Item 3L - Valerie Saveri - PPL Electric  PDF
12.8.2020 Item 3M - Jeff Whitehead - Easter Generation  PDF
12.8.2020 Item 3N - Cullen Howe - Sustainable FERC  PDF
12.8.2020 Item 3O - Mike Jacobs - PJM Planning LGIP  PDF
12.8.2020 Item 3P - Brook Knodel - PJM Interconnection Process Challenges & Possible Improvements  PDF
12.8.2020 Item 3Q - Emil Avram - PJM Interconnection Process Dev Power - Gen Comments  PDF
12.8.2020 Item 3R - Arash Ghodsian - EDFR Queue Slides  PDF
12.8.2020 Item 3S - John Brodbeck - EDPR Interconnection  PDF
12.8.2020 Item 3T - Iker Chocarro - RWE PJM Interconnection Workshop  PDF
12.11.2020 Item 3U - Comments from BayWa Solar Projects LLC  PDF

 10.30.2020 - Interconnection Process Workshop 1 - A Review of the Interconnection Process

 10.20.2020 - PC Special Session - Critical Infrastructure Stakeholder Oversight

 10.9.2020 - PC Special Session - Storage as a Transmission Asset

 9.22.2020 - PC Special Session - Post ISA Education Session

 8.17.2020 - PC Special Session - Pre Queue Education Session

 7.7.2020 - Planning Committee

6.30.2020 Agenda  PDF
6.30.2020 Agenda  DOC
8.5.2020 Minutes  PDF
6.8.2020 Item 3 - Draft Minutes - PC - 6.2.2020  PDF
6.30.2020 Item 4 - Work Plan  PDF
7.7.2020 Item 5A - Phasor Measurement Unit (PMU) Placement Plan in RTEP Planning Process  PDF
6.30.2020 Item 5B - Problem Statement - RTEP PMU Placement  PDF
6.30.2020 Item 5C - Issue Charge - RTEP PMU Placement  PDF
7.6.2020 Item 5D - Solution Proposal - Phasor Measurement Unit (PMU) Placement Plan in RTEP Planning Process  PDF
7.6.2020 Item 5E - Manual 14B - Revision 47 - Executive Summary  PDF
7.2.2020 Item 6 - PJM Load Model Selection for 2020 RRS  PDF
7.2.2020 Item 7A - Order 845 Second Compliance FIling Manual 14A, 14B & 14G Changes  PDF
7.2.2020 Item 7B - Executive Summary Manual Changes M14A Revision 27  PDF
7.2.2020 Item 7C - M14A New Services Queue Process - Clean  PDF
7.2.2020 Item 7D - M14A New Services Queue Process - Redline  PDF
7.2.2020 Item 7E - Executive Summary Manual Changes M14B Revision 47  PDF
7.2.2020 Item 7F - M14B PJM Region Transmission Planning Process - Clean  PDF
7.2.2020 Item 7G - M14B PJM Region Transmission Planning Process - Redline  PDF
7.2.2020 Item 7H - Executive Summary Manual Changes M14G Revision 5  PDF
7.2.2020 Item 7I - M14G Generation Interconnection Requests - Clean  PDF
7.2.2020 Item 7J - M14G Generation Interconnection Request - Redline  PDF
7.2.2020 Item 8 - Attachment M-3 Update  PDF
7.7.2020 Item 9 - Recent Load Impacts  PDF
6.30.2020 Item 10 - Manual 14C - Update  PDF
6.30.2020 Item 11 - State Agreement Approach  PDF
6.30.2020 Item 12 - MEPETF Phase 3 Package C1 Capacity Window  PDF
7.6.2020 Item 13 - Immediate-Need Reliability Update  PDF
6.30.2020 Item 14 - Reliability Compliance Update  PDF
7.6.2020 Item 17 - Update on CCSTF  PDF
7.9.2020 Posting Score Card  XLS

 6.19.2020 - PC Special Session - Critical Infrastructure Stakeholder Oversight

 6.2.2020 - Planning Committee

6.1.2020 Agenda  PDF
6.1.2020 Agenda  DOC
7.9.2020 Minutes  PDF
6.1.2020 Item 3 - Draft Minutes - PC - 5.12.2020  PDF
5.27.2020 Item 4A - Manuals 14A / 14E / 14G Changes  PDF
5.27.2020 Item 4B - Manual 14A - Revision 27 - Executive Summary Manual Changes  PDF
5.27.2020 Item 4C - Manual 14A - Preview - Clean  PDF
5.27.2020 Item 4D - Manual 14A - Redline  PDF
5.27.2020 Item 4E - Manual 14E - Revision 8 - Executive Summary Manual Changes  PDF
5.27.2020 Item 4F - Manual 14E - Preview - Clean  PDF
5.27.2020 Item 4G - Manual 14E - Redline  PDF
5.27.2020 Item 4H - Manual 14G - Revision 5 - Executive Summary Manual Changes  PDF
5.27.2020 Item 4I - Manual 14G - Preview - Clean  PDF
5.27.2020 Item 4J - Manual 14G - Redline  PDF
5.27.2020 Item 5A - 2020 Reserve Requirement Study - Assumptions  PDF
5.27.2020 Item 5B - Reserve Requirement Study Assumptions Letter - 2020 - Clean  PDF
5.27.2020 Item 5C - Reserve Requirement Study Assumptions Letter - 2020 - Redline  PDF
5.27.2020 Item 6A - Phasor Measurement Unit RTEP  PDF
5.27.2020 Item 6B - RTEP Phasor Measurement Unit - Problem Statement  PDF
5.27.2020 Item 6C - RTEP Phasor Measurement Unit - Issue Charge  PDF
5.27.2020 Item 6D - PC Solution Proposal - RTEP Phasor Measurement Unit Placement  PDF
5.28.2020 Item 7 - COVID-19 Impacts & Load Forecast  PDF
6.2.2020 Item 7A - Economic Forecast Update - Post Meeting  PDF
5.27.2020 Item 8 - FERC Transmission Orders Requiring Reallocations & Refunds  PDF
6.1.2020 Item 9 - Order 845  PDF
5.27.2020 Item 10 - Competitive Planner  PDF
6.3.2020 Posting Score Card  XLS

 5.12.2020 - Planning Committee

5.8.2020 Agenda  PDF
5.8.2020 Agenda  DOC
6.3.2020 Minutes  PDF
4.24.2020 Item 3 - Draft Minutes - PC - 4.14.2020  PDF
5.5.2020 Item 4A - Storage as a Transmission & Asset - Problem Statement - Clean  PDF
5.5.2020 Item 4B - Storage as a Transmission & Asset - Problem Statement - Redline  PDF
5.5.2020 Item 4C - Storage as a Transmission & Asset - Issue Charge - Clean  PDF
5.5.2020 Item 4D - Storage as a Transmission & Asset - Issue Charge - Redline  PDF
5.5.2020 Item 5A - MEPETF Phase 3 - Presentation  PDF
5.5.2020 Item 5B - MEPETF Problem Statement Matrix  XLS
5.7.2020 Item 6A - Critical Infrastructure Stakeholder Oversight - Updated Redline Issue Charge - Exelon   PDF
5.7.2020 Item 6B - Critical Infrastructure Stakeholder Oversight - Alternate Redline Issue Charge - DC OPC  PDF
5.11.2020 Item 7 - Reference 03.10.2020 Meeting - PC Synchrophasor Informational Update  PDF
5.7.2020 Item 7A - PMU RTEP  PDF
5.7.2020 Item 7B - PC Problem Statement - RTEP PMU Placement  PDF
5.7.2020 Item 7C - PC Issue Charge - RTEP PMU Placement  PDF
5.7.2020 Item 7D - PC Solution Proposal - RTEP PMU Placement  PDF
5.5.2020 Item 8A - 2020 RRS Assumptions  PDF
5.5.2020 Item 8B - RRS Assumptions Letter 2020 - Clean  PDF
5.5.2020 Item 8C - RRS Assumptions Letter 2020 - Redline  PDF
5.6.2020 Item 9A - Manuals 14A / 14E / 14G Changes  PDF
5.6.2020 Item 9B - Manual 14A - Revision 27 - Executive Summary Manual Changes  PDF
5.6.2020 Item 9C - Manual 14A Preview - Clean  PDF
5.6.2020 Item 9D - Manual 14A - Redline  PDF
5.6.2020 Item 9E - Manual 14E - Revision 8 - Executive Summary Manual Changes  PDF
5.6.2020 Item 9F - Manual 14E Preview - Clean  PDF
5.6.2020 Item 9G - Manual 14E - Redline  PDF
5.6.2020 Item 9H - Manual 14G - Revision 5 - Executive Summary Manual Changes  PDF
5.6.2020 Item 9I - Manual 14G Preview - Clean  PDF
5.6.2020 Item 9J - Manual 14G - Redline  PDF
5.7.2020 Item 10 - Exelon TO Planning Criteria  PDF
5.7.2020 Item 11 - AMPT Planning Assumption Update  PDF
5.5.2020 Item 12 - Dominion Planning Criteria Updates  PDF
5.8.2020 Item 13 - FERC Orders on Transmission  PDF
5.5.2020 Item 14 - TSS Update  PDF
5.5.2020 Item 15 - RC Update  PDF
5.7.2020 Item 16 - COVID-19 Load Impact Update  PDF
5.7.2020 Informational Only - PJM MOD-032 General Summary  PDF
5.6.2020 Informational Only - PJM Queue Status Update  PDF
5.8.2020 Informational Only - Proposed Amendments to Attachment M-3 of the PJM Tariff  PDF
5.14.2020 Posting Score Card  XLS

 2.4.2020 - Planning Committee

1.31.2020 Agenda  PDF
1.31.2020 Agenda  DOC
1.30.2020 2020 Safety Procedure  PDF
1.14.2020 Item 3 - Draft Minutes - PC - 1.7.2019  PDF
1.29.2020 Item 4 - 2020 Annual Meeting  PDF
1.29.2020 Item 5A - TO/TOP Matrix - Revision 15 - Committee Updates  PDF
1.29.2020 Item 5B - Draft PJM TO/TOP Matrix - Revision 14  PDF
1.29.2020 Item 5C - Draft PJM TO/TOP Matrix - Revision 14  XLS
2.4.2020 Item 6 - MEPETF - Phase 3 - Presentation  PDF
2.4.2020 Item 6B - MEPETF - Phase 3 Problem Statement Matrix - Post Meeting  XLS
1.30.2020 Item 7A - Manual 22 Update  PDF
1.30.2020 Item 7B - Manual 22 Update - Executive Summary  PDF
1.30.2020 Item 7C - Manual 22 Revision 18 - Redline  PDF
1.30.2020 Item 7D - Manual 22 Revision 18 - Clean  PDF
2.4.2020 Item 8A - Order 845 - PC Manual Updates  PDF
1.30.2020 Item 8B - Manual 14A - Revision 26 - Executive Summary - Manual Changes  PDF
1.30.2020 Item 8C - Manual 14A - Revision 26 - Redline  PDF
1.30.2020 Item 8D - Manual 14A - Revision 26 - Clean  PDF
1.30.2020 Item 8E - Manual 14E - Revision 7 - Executive Summary - Manual Changes  PDF
1.30.2020 Item 8F - Manual 14E - Revision 7 - Redline  PDF
1.30.2020 Item 8G - Manual 14E - Revision 7 - Clean  PDF
1.30.2020 Item 8H - Manual 14G - Revision 4 - Executive Summary - Manual Changes  PDF
1.30.2020 Item 8I - Manual 14G - Revision 4 - Redline  PDF
1.30.2020 Item 8J - Manual 14G - Revision 4 - Clean  PDF
1.29.2020 Item 9A - Manual 12 Updates  PDF
1.29.2020 Item 9B - Manual 12 - Attachment F - Planning Eligibility Criteria - Redlines  PDF
1.30.2020 Item 10 - Designated Entity Design Standard Bi-Annual Review Updates  PDF
1.29.2020 Item 11 - TPL-007-3 GMD Presentation  PDF
1.29.2020 Item 12 - Critical Infrastructure Stakeholder Oversight  PDF
1.29.2020 Item 13 - Reliability Compliance Update  PDF
2.5.2020 Posting Score Card  XLS

 9.20.2019 - PC Special Session - Merchant Transmission & Offshore Wind(Canceled)

 7.15.2019 - PC Special Session - Merchant Transmission & Offshore Wind

 7.12.2019 - PC Special Session - M-3 Process Lessons Learned

 5.31.2019 - PC Special Session - Merchant Transmission & Offshore Wind

 4.16.2019 - PC Special Session - Merchant Transmission and Offshore Wind

 6.7.2018 - Planning Committee

 3.26.2018 - Special PC - Consideration of Cost Commitment for Evaluation of Competitive Transmission Proposals

 3.6.2018 - Special PC - Consideration of Cost Commitment for Evaluation of Competitive Transmission Proposals

 9.14.2017 - Planning Committee Meeting

 8.10.2017 - Planning Committee Meeting

 7.18.2017 - Special PC Session: Consideration of Cost Cap/Containment Provisions for Competitive Proposals

 5.24.2017 - Special PC Session: Consideration of Cost Cap/Containment Provisions for Competitive Proposals

 2.9.2017 - Planning Committee Meeting

 11.3.2016 - Planning Committee Meeting

 10.18.2016 - PC: New Service Request Study Methods

 9.16.2016 - New Service Request Cost Allocation & Study Methods

 9.2.2016 - Special PC Session: Order 1000

 8.11.2016 - Planning Committee Meeting

 7.14.2016 - Planning Committee Meeting

 4.29.2016 - Special PC Session: Order 1000 Lessons Learned

 2.23.2016 - Special PC Session: Order 1000 Lessons Learned

 8.28.2015 - Long Term Firm Transmission Service (PC)

 6.30.2015 - Long Term Firm Transmission Service (PC)

 3.27.2015 - Firm Injection Rights and Firm Withdrawal Rights Meeting (PC)

 2.12.2015 - Planning Committee Meeting

 8.15.2014 - Energy Storage Participation in RPM Discussion (PC) Meeting(Canceled)

 8.7.2014 - Planning Committee Meeting

 6.5.2014 - Planning Committee Meeting

 3.6.2014 - Planning Committee Meeting

 12.4.2013 - Energy Storage Participation in RPM Discussion (PC) Meeting

 7.12.2012 - Planning committee Meeting

 6.14.2012 - Planning Committee Meeting

 1.12.2012 - Planning Committee Meeting

 12.15.2011 - Planning Committee Meeting

Materials submitted to PJM by PJM Members or any other stakeholder for posting on PJM.com shall not imply support or endorsement by PJM Interconnection.